Project Cycle Management Manual
4. Project Implementation4. Project Implementation 4. Project Implementation4.1 Key Stakeholders in Project ImplementationA number of stakeholders are involved in the implementation of projects. Key stakeholders responsible for project implementation are:
Key persons appointed by each key stakeholder are shown in Figure 4.1. Responsibilities and tasks of the key stakeholders and key persons are described in the following sections. 4.1.1 The Project HolderResponsibility of the project holder At one extreme, the implementation may rely almost entirely on the project holder; at another extreme, the beneficiary or other stakeholders may implement major parts of a project. As a general rule, DEPA will hold a project holder responsible for the achievement of
the immediate objectives of the project, but the particular capacity or role of the
project holder as specified in the project document may modify this responsibility. DANCEE's prior or subsequent approval of proposals, initiatives and approaches does not limit the professional responsibility of the project holder in terms of the appropriateness or feasibility thereof, unless the project holder in advance explicitly has alerted DANCEE to particular risks associated therewith. This also applies to any information on the progress or quality of the implementation provided by the project holder to DANCEE in reports, etc. Figure 4.1: Key Stakeholders
The project holder will assign a team of international and national experts to implement the project. The project holder will appoint a team leader and a project director. The project director will be responsible for quality assurance of the project implementation and project outputs. The team leader has the overall daily responsibility for the timely and correct implementation of the project. In most projects the project holder will also assign a local assistant team leader. Team leader The team leader is expected to establish a smooth working relationship with the local project manager, local consultants and other stakeholders. Further, the team leader will draft the specific work plans for all experts involved in the project and supervise the work performed. The team leader will be responsible for organising a steering committee (SC) and - if agreed - also a advisory committee - please refer to Sections 4.2.2 and 4.2.3. The team leader will act as secretary to the steering committee and the possible advisory committee. In particular, the team leader will ensure:
4.1.2 The BeneficiaryResponsibility The beneficiary will have the overall responsibility for implementation of local
project components. The responsibilities of the beneficiary will be clearly defined in the
project document. A representative appointed by the beneficiary serves as deputy chairman of the steering committee and chairs all meetings of the advisory committee - please refer to Sections 4.2.2 and 4.2.3. Local project manager 4.1.3 The Ministry of EnvironmentResponsibility of MoE Local project director 4.1.4 DANCEEResponsibility of the country coordinator Local project coordinator The LPC will monitor project implementation by visiting the project implementation sites regularly. Inadequate performance in relation to the project document will be reported to DANCEE. The project holder will then be contacted by DANCEE in order to find possible solutions to the problems incurred. The local project coordinator does not, however, have the authority to demand changes in project implementation. DANCEE can stop project implementation 4.2 Management ForumsTo ensure the efficient implementation of projects, each DANCEE project will establish a management structure for project implementation. The type of management structure established will depend on the particular tasks of the project. The management structure will be described in the project document and will be elaborated in the procedures manual - please refer to Section 4.3.5. 4.2.1 Project Management GroupResponsibilities The team leader is responsible on behalf of the project holder and the local project manager is responsible for inputs from the beneficiary. The tasks and responsibilities of the team leader and the local project manager are described in the project document and shall be elaborated in the procedures manual. 4.2.2 Steering CommitteeFor most projects, DANCEE recommends a steering committee. Some projects, e.g. projects which basically consist of equipment deliveries may not require a steering committee. Established by Project Holder Members
The steering committee may be expanded as appropriate to include:
Responsibility First steering committee meeting Final steering committee meeting Project sustainability Costs of steering committee meetings 4.2.3 Advisory CommitteeThe MoE and the beneficiary may decide to establish a project advisory committee to follow the development of the project implementation. Members of a project advisory committee will typically represent local and regional authorities, organisations, educational institutions, research institutes, NGOs, independent experts, citizen's groups and other stakeholders. A representative appointed by the beneficiary chairs all meetings of the advisory committee. No formal responsibilities The project budget may have a small provision for to meet the costs of advisory meetings. 4.3 Project Monitoring and Reporting4.3.1 Project Monitoring SystemsMonitoring system Each DANCEE supported project is required to establish a monitoring system at the start of the project. The aims of the monitoring system are:
Issues to be monitored Table 4.1: Issues to be monitored
Evaluation The effectiveness of the project is judged by an assessment of the extent to which the project has achieved its immediate objectives. The foreseen and unforeseen consequences of a project, to the beneficiary in particular, and to society in general, shall be assessed. The project's effectiveness and impacts shall be assessed by the project holder as part of the completion report. In addition, DANCEE can decide that the project should undergo an external evaluation according to the guidelines in Section 5. The monitoring system should normally ensure that baseline data are available against which to assess the environmental impact of a project. Baseline measurements or estimates should be made both before and after project implementation in order to measure the environmental impacts of the project - please refer to Section 4.3.3. Indicators An indicator should be:
The list of indicators used by DANCEE as part of the statistical summary is provided in Enclosure H. Some examples of typical indicators are:
Milestones Specifying indicators and milestones 4.3.2 ReportingDuring project implementation, the project holder is responsible for the production of the reports specified in the project document. Reports normally include monitoring reports, management reports and technical reports. The different reports to be presented by the project holder are outlined in Figure 4.2. Figure 4.2: Reports produced during project implementation
Technical reports
Reporting monitoring results The project reporting system is based on three types of monitoring reports:
In addition to the above monitoring reports, a baseline study/description should be part of the project's monitoring and evaluation system. Formats and requirements for the individual reports are outlined below. 4.3.3 Baseline DescriptionsA baseline description is established with the aim of describing the existing situation (the baseline) against which the impact of a project can be measured. DANCEE requires baseline descriptions Two examples of baseline descriptions are given below. Baseline for waste water treatment Existing waste water treatment facilities will be evaluated and a baseline describing the present treatment facilities, their efficiency and the level of pollution from the discharge of waste water will be established. Next, an assessment will be made of the improvements in the waste water treatment required to meet an outlet quality equal to e.g. EU standards and the expected consequent effect on the receiving waters. In some projects, it is not possible to measure the direct impact of the project on the environment. In these situations, the baseline can be established by a comparison with the pre-existing processes. Two examples are given below of baseline studies for projects with no direct, measurable environmental impacts. Baselines for legislative assistance Baselines for technical studies An example of such evaluations is related to the Integrated Pollution Prevention Control (IPPC) Directive in European countries. From an evaluation of existing production facilities in industrial units, a baseline describing production facilities and levels of pollution control is established. Next, an assessment is made of modified production capability and pollution prevention measures based on the introduction of Best Available Technology (BAT), also in accordance with the IPPC Directive. All achievements are described in relation to the baseline situation. 4.3.4 Approval of ReportsReports need to be approved first by the steering committee and subsequently by DANCEE. The general procedures for the approval of project reports are described below. The steering committee Rejections of reports The project holder may request the chairman to ask the MoEE representative to participate in this further meeting, whether or not the MoEE representative took part in the meeting which rejected the original report. Once such a request has been submitted, the meeting cannot be held without the MoEE representative being present. In those cases where the MoEE representative participates in the steering committee meetings, all reports are approved if the MoEE representative has no objections. DANCEE's approval of reports DANCEE's approval of reports does not limit the professional responsibilities of the project holder - please refer to Section 4.1.1. 4.3.5 Inception ReportTypically all tendered projects have an inception phase and an inception report,
whereas some projects by application, and most equipment supply projects do not have an
inception phase. The project document will specify whether the project requires an
inception phase. The usual length of the inception phase is three months. Inception phase
The procedures manual and the baseline study will be attached to the inception report. The draft inception report shall normally be submitted to the steering committee and DANCEE at least one month before the first steering committee meeting. Assessment of project document The assessment of the project document is intended to verify that the description of the context, problems and assumptions for the project remain valid. In addition, the adequacy of inputs and support from the implementing organisation and other parties will be assessed, and clear roles and responsibilities will be defined. The assessment will also verify that the outputs can be produced with the planned activities and inputs specified in the project implementation plan. The indicators and means of verification will be detailed and refined, and the adequacy of baseline data will be checked. Adjustments to project document Approval of inception report
|
![]() | the indicators and milestones to be monitored, |
![]() | how data will be compiled, |
![]() | persons responsible for compiling the data and reporting problems, |
![]() | persons responsible for remedial actions. |
Table 4.3: Procedures Manual Format (example)
Table of contents |
I. Cover sheet |
1. Project organisation, institutional relationships and responsibilities: Distribution of responsibilities among the beneficiary organisation, MoE, DEPA, country coordinator, project management group and staff, steering committee, external parties, and other stake-holders. |
2. Lines of communication: procedures for communication among the beneficiary organisation, MoE, country coordinator, project management group and staff , steering committee, external parties, and other stake-holders. |
3. System and procedures for filing and documentation. |
4. Staff rules: provisions regarding working hours, field trips, leave, etc. for national and international project staff. |
5. Project monitoring: management procedures for project monitoring, including the establishment of baseline data and indicators for project monitoring and evaluation. |
6. Financial procedures: procedures and responsibilities should be defined in relation to the following matters: (i) preparation and approval of internal budgets; (ii) approval of expenditures; (iii) payment of bills and collection of receipts, and (iv) handling of cash. |
7. Project assets: inventory, control, and use of project assets, including vehicles, equipment, facilities, etc. |
8. Quality assurance: procedures and plans for assuring the quality of project outputs, including reports and other documents. |
Format of manual
Table 4.3 suggests contents and format for a procedures manual, but a manual will
always be project-specific. Thus, it may contain additional information that project staff
and steering committee may find appropriate. The physical format should be flexible (ring
binder as well as electronic format) to allow continuous updating during the project's
lifetime.
Progress reports are prepared by the project management group at the initiative of the team leader. They are normally submitted to DANCEE and the steering committee every three months. The scheduling of progress reports is established in the inception report, and progress reports should to the extent possible correspond to the planned achievement of project outputs.
Means of communication
The progress reports (max. 10 pages plus annexes) are a means for the project
management group to communicate information about the implementation of the project to the
steering committee, MoE, DANCEE and other stakeholders.
Focus on problems
Progress reports should not repeat information contained in previously submitted
reports. Their prime function is to point to unexpected problems which have occurred in
the reporting period or which can be foreseen. Progress reports should propose solutions
to identified problems for approval by the steering committee and DANCEE. These reports
will also allow controlled adjustments, convey information to stakeholders, and serve as a
project diary, showing agreed alterations to the project document.
DANCEE will primarily use the progress reports to monitor project implementation and will not normally initiate action unless specifically requested by the team leader or by MoE, or in cases where it is obvious that project implementation is not progressing satisfactory.
Approval of progress report
The draft progress report is normally submitted to the steering committee and DANCEE
at least ten working days before the steering committee meeting. The steering committee
comments on the draft progress report which is submitted to DANCEE after the meeting.
DANCEE shall approve the report in writing within ten working days upon receipt of
comments from the steering committee. If DANCEE cannot approve within ten working days,
notice shall be given in writing to the project holder.
Approval of changes
If changes to the project outputs or objectives become necessary, these will be
presented and documented in the progress reports. Proposed changes should be listed in the
covering letter to the progress report for subsequent approval by DANCEE. Adjustments will
be approved only when the covering letter is signed by DANCEE and the project holder -
please refer to Enclosure F.
Adjustments of budget lines
Adjustments of budget lines are possible to a limited extent in tendered projects -
please refer to Section 4.4. For projects by application, adjustment of budget lines is
only possible to a limited extent and only after DANCEE's approval. Accounts for
reimbursable expenses and accounts for fees should be submitted at the same time as
progress reports. Payments cannot be made without approval of submitted progress reports.
A suggested format for progress reports is shown in Table 4.4. However, the reports may
contain additional information found appropriate by the project management group.
Table 4.4: Progress Report Format
Covering letter, please refer to Enclosure F | ||||||
Table of contents | ||||||
I. Cover sheet II. Executive summary |
||||||
1. Project context: review of project assumptions in the light of any new problems or opportunities. | ||||||
2. Project outputs: review of project outputs and Indicators achieved and/or due during the reporting period. | ||||||
3. Project activities: review of implementation of activities according to plan. | ||||||
4. Project inputs: review of project inputs used during the reporting period. | ||||||
5. Financial statement: overview of the financial situation of the project compared to the budget, and requests for budget changes (if any). | ||||||
6. Project implementation status: problems and
opportunities (if any) encountered during the reporting period not covered elsewhere in
the report, such as: (a) analysis of possible unintended impacts and suggestions for action; (b) review of likelihood of achievement of project objectives; (c) review of overall project strategy; and (d) analysis of project sustainability. |
||||||
7. Revisions to project implementation plan (PIP) or project document (if any). | ||||||
Annexes
|
||||||
Technical reports may include masterplans, feasibility studies, manuals, tender documents etc.
The technical reports can be used as milestones and it must be specified in the project document which technical reports are required.
The technical reports must be submitted to DANCEE in accordance with the time scedule
in the project document. DANCEE shall approve the report within 20 working days upon
reception. This approval must be in written form and addressed to the project holder.
At the initiative and responsibility of the team leader, the team leader and the local project manager will prepare a draft completion report prior to the end of the project. The primary purposes of the report are:
![]() | to document the status of the project at the time of completion, i.e. to what extent the outputs have been produced and the objectives achieved, or are likely to be achieved, |
![]() | to provide an assessment of the need for possible further assistance from DANCEE or other sources, |
![]() | to contribute to the accumulation and dissemination of experience, |
![]() | to provide a basis for evaluation. |
The team leader will submit the draft completion report to the steering committee. The steering committee will discuss the draft completion report. The draft completion report will be sent to DANCEE in two copies after approval by the steering committee.
Approval of completion report
The draft completion report is normally submitted to the steering committee and
DANCEE at least one month before the steering committee meeting. After the steering
committee, comments are submitted to DANCEE. DANCEE shall approve the report in writing
within 20 working days upon receipt of the comments. If DANCEE cannot approve the report
within 20 working days upon receipt of the comments from the SC, notice will be given in
writing to the project holder.
Final completion report
If there is no request for changes, the draft completion report will become final by
a replacement of the cover page. If the steering committee or DANCEE request changes, a
revised draft completion report will be submitted by the team leader to the chairman of
the steering committee and to DANCEE within 10 working days of receipt of the steering
committee's or DANCEE's comments. If the project holder does not receive any comments from
the steering committee or DANCEE within 20 working days, the revised draft completion
report may be considered approved.
Statistical summary
DANCEE maintains a database of all projects carried out under the DANCEE programme.
This database contains e.g. information on environmental impacts, ex-post summary,
co-financing. All DANCEE projects must be included in this database. For this purpose, a
statistical summary for each project must be filled in.
The project holder is responsible for filling in the data necessary in the statistal summary at the end of the project. The project holder shall submit the statistical summary (in MS Word format) together with the completion report. The summary must be filled in in accordance to specific instructions and submitted to DANCEE on diskette.
With the approval of the completion report and the statistical summary, the project holder may submit his final accounts and invoice.
The project holder will have completed his services once the completion report, the statistical summary and the final accounts have been accepted by DANCEE.
A format for the completion report is shown in Table 4.5.
Table 4.5:Completion Report Format
Table of contents | ||||||||
I. Cover sheet II. Map of location III. List of abbreviations IV. Executive summary |
||||||||
1. Introduction: brief description of the project and its background. | ||||||||
2. Project context: review of project assumptions and any alternative opportunities | ||||||||
3. Project outputs: review of all project outputs | ||||||||
4. Project inputs: review of all project inputs, including international and national staff inputs, equipment, facilities, etc. | ||||||||
5. Financial statement: overview of the financial situation of the project compared to the budget at the time of project start. Complete audited accounts must also be included. | ||||||||
6. Project sustainability: assessment of sustainability. | ||||||||
7. Impact assessment: preliminary evaluation of project effectiveness in achieving its o.Objectives and of any unintended impacts. | ||||||||
8. Recommendations: summary of recommended follow-up actions by the project holder, the beneficiary, MoE and by DEPA (including recommendations for a formal, independent project evaluation, if appropriate). | ||||||||
9. Lessons learned: summary of experience that may be of general interest, and of any achievements or obstacles that have not been described above, including an assessment of overall project strategy. | ||||||||
Annexes
|
||||||||
The purpose of this Section is to provide an overview of DANCEE's terms of payment and requirements for financial reporting. It is for information only, has no legal status, and can be deviated from by the DANCEE. The legal and detailed terms and requirements for a specific project are specified in the contracts and the letter of grant.
Project holder's responsibility
The general responsibility for the financial management of funds provided by DANCEE
to projects rests with the project holder.
Financial management responsibilities entail inter alia that all fees and reimbursable expenses invoiced to DANCEE are against specific provisions in the budget and are adequately supported by evidence that procurement is based upon fair and open bargaining or tendering and on competitive terms and conditions, and that the use of the funds is appropriately accounted for. In general, financial management must be in accordance with common professional principles of sound commercial practice.
DANCEE cannot accept that any offer, payment, consideration, or benefit of any kind, which constitutes an illegal or corrupt practice, shall be made or accepted, directly or indirectly, as an inducement or reward in relation to the tendering, award, execution or performance of a contract or a grant. Any such practice will be grounds for the immediate termination of a project. The project holder will be permanently disqualified from DANCEE funded projects and activities. DANCEE may also pursue further civil and criminal actions against the project holder.
DANCEE will pay the project holder for fees and reimbursable expenses which are specified in the budget and incurred in the implementation of the project within the budgeted amounts.
Payments will be made on the basis of invoices submitted to DANCEE by the project holder.
Projects by Tender
Advance payment
In projects by tender, DANCEE may make advance payments to the project holder upon signing
of the contract in an amount corresponding to a maximum of 30 % of the total estimated
fees and to a maximum of 40 % of the total estimated reimbursable expenses. An advance
payment must be repaid by means of pro rata deductions from the subsequent progress
payments to the project holder.
Project holders other than NGOs must provide a security (bank guarantee) for an advance payment. For advance payments of less than DKK 400,000, DANCEE may waive this requirement.
DEPA may conduct an assessment of the institutional and financial standing of a NGO for
purposes of determining the size of the advance payments.
Progress payments
Progress payments are made quarterly. DANCEE's approval of the most recent progress
report is a precondition for the progress payment.
Progress payments are made on the basis of invoices submitted to DANCEE by the project holder for the services rendered and for the reimbursable expenses actually incurred in the preceding quarter.
Final payment
In a KR-contract, the advance and progress payment can as a maximum amount to 75% of
the total estimated fees and reimbursable expenses. A final payment is made after DANCEE's
approval of the final accounts.
For the procurement of supplies and works, DANCEE and the project holder may agree that DANCEE pays directly to the supplier or contractor on the basis of invoices endorsed for payment by the project holder.
Projects by Application
In projects by application, DANCEE will disburse the grant in two instalments.
First instalment
The first instalment corresponding to 90% of the grant will be paid at the time of
submission of the completion report. If DANCEE at this point of time should have any
substantial objections to making the payment, DANCEE may postpone it until DANCEE has
approved the completion report and the audited final statement of accounts.
Second instalment
The second instalment (10% of the grant) will be paid when DANCEE has approved the
completion report and the audited final statement of accounts.
The project holder shall submit invoices for the payment of the instalments.
Quarterly payments in projects longer than 6 months
In projects with a duration of more than 6 months, DANCEE may agree to make payments
on account at quarterly intervals in amounts which correspond to fees and reimbursable
expenses accrued in the preceding quarter. These payments cannot in total exceed 90% of
the grant. Payments on account will not be finalised until DANCEE has approved the
completion report and the audited final statement of accounts.
Advance payments to NGOs
Advance payments to NGOs are made in amounts which are suited to the accrual of fees
and reimbursable expenses. Normally, DANCEE makes quarterly or biannual advance payments
in amounts which correspond to the budgeted fees and reimbursable expenses in the
following period.
DEPA may conduct an assessment of the institutional and financial standing of a NGO for purposes of determining the size of the advance payments.
Advance payment for supplies and works
Advance payments in connection with the procurement of supplies or works may
correspond to maximum 75% of the costs. Such advance payments are subject to separate
agreement between DANCEE and the project holder.
Project holders other than NGOs must provide a security (bank guarantee) for an advance payment. For advance payments of less than DKK 400,000 DEPA may waive this requirement.
Direct payment to supplier or contractor
For the procurement of supplies and works, DANCEE and the project holder may agree
that DANCEE pays directly to the supplier or contractor on the basis of invoices endorsed
for payment by the project holder.
DANCEE will pay the invoices within a period of 30 days from receipt provided that the invoices are complete and not disputed and that the project holder has submitted requisite reports.
Payment of the invoice as of 31 December and the final invoice further require the submission of the annual or final statement of accounts.
VAT and Taxation
In a project by application, the grant is not subject to Danish VAT, but the grant is
taxable income for the project holder.
Services, supplies and works under a contract with a Danish project holder or subcontractor are not subject to Danish VAT, if the deliverables exclusively are used outside the EU.
All funds from the DANCEE shall be exempted from VAT, duties and taxation in the partner country.
Statements of account
DANCEE may require that the project holder submits audited annual and final
statements of accounts to DANCEE within a period of three months after December 31 or
after completion.
In projects by application, the requirement for annual statements of accounts only applies if DANCEE has agreed to make payments on account.
For longer projects, the first annual statement of accounts and the final statement of accounts may cover a period of up to 14 months, and the consultant needs not submit annual statements of accounts within that period. The consultant shall in advance notify DANCEE of the omission of an annual statement of accounts.
The annual statement of accounts shall include a budget for the remaining project period.
The statements of accounts shall be in accordance with the specifications issued and be in the form which DANCEE may require at any time. Please refer to Table 4.6.
Audits
The annual and final statements of accounts shall be audited, and the auditor shall
render his opinion and sign the statements.
The auditor shall be a state authorised or registered accountant.
The audit shall be conducted in accordance with standard auditing practice and any particular instructions issued by DANCEE.
The costs of the audits may be included in the budget as a reimbursable expense and invoiced to DANCEE.
Other donors
In case of projects which have been co-financed by funds from DANCEE and funds from
other donors or financial institutions, DANCEE shall receive a copy of the auditing report
from the entire project.
Inspection
DANCEE and its representatives shall be entitled to inspect and otherwise examine the
project, including (but not limited to) all and any accounts, receipts, vouchers,
contracts, and make site inspections, during and after the project. The project holder and
the beneficiary are required to grant access for such inspection and examination. This
also applies to investigations conducted by the office of the Auditor General of Denmark.
Table 4.6: Annual State of Accounts Format
Reporting Period: |
Thousands of Danish Kroner |
Budget Line | Description | A Budgeted Amount (pro.doc.) |
B Total in Previous Periods |
C Expendi-ture in Current Period |
D Budget for remaining project period |
A-(B+C) Balance Remaining |
% Remaining |
Fees | |||||||
1. | |||||||
2. | |||||||
3. | |||||||
Sub-total | |||||||
Reimbursables | |||||||
1. | |||||||
2. | |||||||
3. | |||||||
Sub-total | |||||||
Equipment | |||||||
1. | |||||||
2. | |||||||
3. | |||||||
Sub-total | |||||||
Total | |||||||
Contingency | |||||||
Grand Total (incl contingency) |
[Front page] [Contents] [Previous] [Next] [Top] |