| Front page | | Contents | | Previous
| | Next |
Cleaner Technology Projects in Denmark 1997
Miljørigtig projektering ved renovering af boligbyggeri i Ballerup
Arbejdsrapport nr. 36, 1997, Miljøstyrelsen
Problems with the indoor climate and humidity at Lundegården I in Albertslund have
resulted in a radical renovation of the buildings. This project deals with the
environmental management of the renovation of a residential construction in
Ballerup.
Lundegaarden I is a housing scheme with a total of 628
dwelling units. The scheme was completed in 1969.
The houses are attached, constructed in sandwich elements of concrete, supplemented
with light elements as facades, roofs and internal walls. The roofs are flat clad in roof
paper. The crawl way design is without any moisture membrane towards the soil. Each house
is provided with a garden to which the light facade walls face. The heavy gables and
facades, which only in some few houses have windows, are directed towards the local paths.
As for many projects, economy and functional and architectural requirements have more
or less outruled the environmental requirements. In the housing scheme, Lundegaarden I,
the problems connected to fungi have concerned the working method as well as the suggested
solutions, so that environmental management in the project design in practice has been a
supplement to the ordinary design.
Lundegaarden I has had much public attention partly due to political reasons and partly
to economic reasons. The design has thus not adhered slavishly to the normal phase
distribution, since considerations of for example "demolition or not" have been
taken simultaneously with the assessment of actual suggested solutions.
Prior to commencement, a technical audit was carried out to establish the actual extent
of the mould problems.
In the environmental programme some environmental impacts were chosen and described in
principle and prioritised. The indoor climate was the subject matter of the renovation
project and it was given high priority. As an ultimate requirement the mould and moist
problems should be removed.
As is common practice in connection with most renovation projects, the energy
consumption should be reduced. Neighbour inconvenience would as a natural consequence be
taken into consideration due to the large extent of the renovation work. The work
environment and the solid waste problems were given higher priority due to the extensive
mould attacks.
During the programme phase the "environmental management circle" was
discussed several times - more or less systematically. Certain problems were elaborated,
while others were subject to only a sporadic investigation. The systematics were always
"inventory - assessment - documentation".
Four more or less parallel investigations were carried out. (I-IV).
In all investigations the evaluation parameters were consistent, regardless of the type
and level of the investigations. The result has been that the considerations on indoor
climatic problems currently have been supplemented with considerations on energy
consumption, work environment, neighbour inconveniences and solid waste.
The technical investigation showed that the mould attack was very extensive. The
consequences of this fact meant that the renovation of Lundegaarden I could be so
comprehensive that a total demolition of the housing estate and reconstruction was a
realistic alternative. The conclusion was that a renovation should be carried out. This
was not due to considerations to the environment, but primarily to the architectural
values of the housing estate.
When it was decided to aim at a renovation, which apparently would be very costly, it
was considered to divide the renovation into two or more phases. The conclusion was that
the renovation should be in one phase, as the environmental impact at more renovations
would be heavier. The reasons are larger amounts of solid waste and inconveniences to the
residents as well as destruction of the area and a poorer working environment in
connection with repeated renovations.
For communication to the residents and politicians a preliminary design was prepared
illustrating different solution models. The conclusion suggested a total renovation in
which all building components should be removed and rebuilt - except of foundations and
heavy external walls.
The Consultants radical suggestion of an almost complete renovation of
Lundegaarden I resulted in some critical remarks. Therefore, an external expert group was
established to assess these and to investigate whether it would be possible to establish
more economical renovation methods, which could ensure a satisfactory indoor climate.
The conclusion was that the original suggestion should be implemented. Among other
things it was due to the lack of existing documented experiences in fungi damage
establishing the extent of necessary and sufficient renovation measures. The Health
Authorities could thus not accept solutions, which did not completely remove the micro
fungus problems.
Environmental impact assessment on building components was already carried out in
connection with the preparation of the building programme. Therefore the pilot project was
primarily designed to investigate the environmental problems connected to an
industrialised production as opposed to construction in situ.
The conclusion was that the industrialised construction - everything taken into
consideration - would result in a better work environment, less neighbour inconveniences
and less waste. This is primarily due to the fact that the industrial process is easier to
manage than the craftsman methods.
Author/ institution
Birch & Krogboe
Blad & Thygesen A/S
KAB Construction- & Building Administration S.m.b.a.
This report is subsidised by the National Council for Recycling and Cleaner Production
ISSN no. 0908-9195
ISBN no. 87-7810-791-1
| Front page | | Contents | | Previous
| | Next | | Top | |