Water Prices in CEE and CIS Countries. Volume II: Case Studies Chapter 3.
|
|
117,416 m 3 /day; 246 lcd; 143 lcd; 62 lcd equal to 20%. |
This means that the domestic consumption comprises about 58% of the total consumption. The domestic unit water consumption (143 lcd) is comparable to unit demands in North-western Europe. The UfW is not excessive.
3.5 Water and Wastewater OperationsThe water supply provides 100% coverage of 24 hours supply per day at a design pressure of minimum 5 m. Reportedly only a few minor areas face pressure problems.
As mentioned above, the water leaving the water treatment plants fulfils applicable water quality standards, and only a few samples, which reach the consumers exceed the standards. The most frequent parameter for non-fulfilment are iron, manganese, turbidity and colour, and to a minor degree bacteriological parameters. This means that the water quality changes in the network, mainly due to the ferrous materials (with regard to the chemical parameters) and due to polluted reservoirs or leaks (with regard to the bacteriological parameters).
The number of recorded breakdowns is 42 per km per year for water pipes (115 per km per year if connection pipes are included) which is lower than, for instance, Brno, and much lower than for most CIS countries, but much higher than, for instance, in Scandinavia.
The number of blockages in the wastewater network is 280 per km per year, which is quite high (eg. six times the average for UK); and substantially higher than, for instance, Brno.
The annual rehabilitation intensity has been estimated at:
![]() | Water pipe network: 0.9% which appears on the low side, but reasonable. The number of failures appear to be high compared to a corrosion condition assessment made during the Technical Audit. This corrosion assessment suggests that 8% of all iron pipes (ie about 73 km of pipes) have through-thewall corrosion and need to be replaced. It is estimated that a further 0.3% of the pipes will become fully corroded per year; |
![]() | Wastewater collection network: 0.2%, which also appears on the low side, but reasonable. CCTV inspections have begun but only a limited part (< 5%) of the network has been inspected. The Technical Audit suggests that 42 km of wastewater collectors (6%) are to be upgraded within 5 years. |
The staff of the water and wastewater utility comprises 998 employees. Selected staff efficiency indicators are:
|
0.68 57 2.03 |
These indicators are comparable with other CEE countries. Compared to North-western Europe the staffing is high.
3.7 InvestmentsThe firm Aqua has, in 1996, outlined an investment programme for PWiK, but it is based on demographic and water demand projections which have become outdated. Furthermore, the investment programme anticipates a severe present condition of the water and wastewater networks. In connection with the preparation of a concept paper for the restructuring of Posnan water and wastewater company in 1998, some preliminary adjustments to the investment programme were proposed, without actually making detailed technical assessments.
Finally, a full technical review has been made by VA Projekt.
The investment programmes are summarized in the following table; all figures in Mill USD:
Table 3.1:
Investment Programmes
According to discussions with PWiK, the annual "internal" investments for 1999 and 2000 are about 40-50 mill PLN/yr. (10 mill USD/yr.). It should be noted that the City finances most development investments, for instance 85% of the Central WWTP, scheduled for completion ultimo 2000.
The completion of the Central WWTP will result in increased O&M costs notably for power supply and general maintenance of the 350 mill PLN investment (this has been taken into account in the financial model of Booz-Allen & Hamilton).
The overall tariff increases for various levels of investments have been assessed in the financial model of Booz-Allen & Hamilton. The results are illustrated in Figure 3.1.
Figure 3.1:
Relationship between medium term investments and resulting tariff increases, Poznan
1998 - 2005.
With regard to the required investments for water pipe renovation, it appears that the Technical Audit recommendations will result in investment levels closest to the Booz-Allen estimates. It is consequently anticipated that the level of investments of the Technical Audit will be of the same order as those of the Booz-Allen & Hamilton estimates, ie at about 50 mill USD for the period 1998-2005. This means that we are at the lower end of the curve shown above, say at about a 20% increase in tariffs.
If the PWiK were to the finance full cost of completion of the COS WWTP (estimated 44 mill USD by Booz-Allen), the 1998-2005 investments will be about 100 million USD, and the tariff increases will be up to 60%.
The current level of PWiK investments of about 10 mill USD annually will require an approximate 20% increase in tariffs (one time).