Guidelines on remediation of contaminated sites

Appendix 4.1
Instructions for carrying out borings and wells.

This Appendix describes how to carry out borings and wells conducted in connection with contamination investigations. In addition to drilling, screen installation and grouting the well casing is also covered. The following points are addressed:
Drilling
Maintaining records
Screen installation
Grouting well casing
Measuring-in and levelling

Soil sampling is covered in Appendix 4.2, water sampling in Appendix 4.3. It has been the intention to develop the following as a set of minimum requirements that should be met when drilling. As a consequence, this Appendix can be included as the basic requirements in connection with submission of tenders for drilling and well construction. Additional requirements must be formulated in relation to the purpose and nature of individual investigations.

Statutory Order No. 4 (4 January 1980) on the execution of wells for groundwater /3/ specifies present regulations for drilling, abandoning, construction, and notification, etc. According to the Statutory Order on design of wells for groundwater, GEUS must be notified within three months of drilling of any wells serving this purpose.

The designation ’localisation borings’ is used to denote soil borings conducted in order to identify and describe contamination of the upper soil strata and groundwater aquifers near ground level. Such borings are often used during the preliminary stages of the investigation process.

In connection with very shallow soil borings (1-2 m) , hand drilling is possible. For this purpose a post-hole auger or a spade drill can be used (Dutch drilling equipment) /1/. Otherwise, shallow exploratory soil borings are usually carried out using a solid-stem auger or a bucket auger as drilling tool. If geological conditions permit, the borings can be executed without the use of casing, since this method can provide adequate level-specific soil samples in connection with shallow borings (to a depth of approximately 3 m and above groundwater level).

In principle, the dimension of the borehole is discretionary. The choice of dimensions must be consistent with any desired screen size, including the gravel pack. Normally, a screen with a diameter of 63 mm (50 mm) is inserted in 6" soil borings, whereas only a 25 mm piezometer can be placed in 4" soil borings. If screens are installed in an actual groundwater aquifer, the well casing should always be grouted with bentonite, typically at the level of any low-permeable strata. Figure 1 features an example of a screen installation.

Shallow localisation soil borings can be filled back with the excavated material if the soil borings do not exceed a depth of 3-4 m, or if they do not cut through more than one groundwater aquifer.

In contrast to the shallow localisation soil borings, casing should always be used during the drilling of investigation borings. This is due to the fact that these borings are deeper, and that satisfactory sampling is usually the objective, either of soil or water or both. The use of casing will prevent cross contamination between the various strata. Also, the use of casing is necessary when drilling below the groundwater level

Normally, augering is used. However, with non-cohesive soil (sand/gravel) below groundwater level, the cable tool method will often be used /1/. When using a cable tool, water is usually added. It is necessary to be aware of this in connection with subsequent water-sampling, where removal of stagnant water is particularly important to facilitate representative sampling.

Other drilling techniques may be appropriate to the extent that no soil samples are required or that an impaired quality and/or quantity of geological information is acceptable. Such techniques might for include e.g. driven well or drilling with a hollow-stem auger. Deep investigation borings should not be located in the most contaminated areas (hot spots) of a contaminated site /2/.

One of the primary targets of investigation soil borings is to ensure the water sampling over a long period, at specified depths, through a screen. As a consequence, the dimensions of soil borings must be selected according to the desired screen installation. Screen dimensions are selected according to the purpose of the soil boring. Typical associated dimensions and maximum pumping yields are presented in Table 1.

Table 1
List of recommended screen dimensions

Purpose

Minimum screen
diameter/ mm

Field measurements or sampling with suction pump etc.

25 (21.5 mm inside)

Sampling with smallest submersible pump (max yield approx. 2 m3/h)

63 (52 mm inside)

Pumping with smaller submersible pumps (max yield approx. 15 m3/h)

110 (99.4 mm inside)

Pumping with larger submersible pumps (max yield approx. 15-40 m3/h)

160 (149 mm inside)

Pumping with larger submersible pump (max yield approx. 40-80 m3/h)

225 (203 mm inside)

Pumping with largest submersible pump (max yield approx. 40-80 m3/h)

315 (285 mm inside)


The connection between the above maximum yield values and the associated minimum dimensions must be seen as guidelines. The above values are determined using the dimensions for commonly used submersible pumps (such as GRUNDFOS type). Attention must be drawn to the fact that pump types exist with different dimensions, and to the fact that the water head influences pump yield.

Table 2 presents guidelines for the connection between borehole dimensions and screen dimensions. The recommended screen dimensions should not be exceeded, as this will result in and insufficient gravel pack and grouting.

The borings must be protected at ground level by a concrete protective casing with a cap, or by installing dry wells. Wells to deeper groundwater aquifers must be fitted with lockable seal caps or covers.

Table 2
List of recommended screen dimensions

Borehole diameter

Screen diameter/ mm

4" = 100 mm

25, (50)

6" = 150 mm

63, (90)

8" = 200 mm

110, (125)

10" = 250 mm

160, (140)

12" = 300 mm

200, (160, 225)

16" = 400 mm

250, (315)

The designation ’wells’ denotes borings whose construction correspond to water-supply wells. The primary purpose of these borings is to pump up groundwater from a groundwater aquifer, whereas soil samples from these borings are only used for geological assessment and are analysed only if contamination is registered during boring. Borings of this kind are primarily used for monitoring groundwater, and sometimes for remedial pumping. With the exception of remedial borings, wells should not be located in the most contaminated areas (hot spots) of a contaminated site /2/.

When carrying out control wells outside the contaminated site, there is basically freedom of choice as regards drilling method. This means that rotary drilling or air drilling, e.g. Odex drilling might be considered. These methods can be advantageous in connection with solid rock such as carbonate deposits. /1/. When carrying out rotary drilling, where drilling fluid is added to the borehole, the chemical content of the fluid should be tested. It is also particularly important to carefully remove the drilling fluid by developing the well before water sampling takes place. Rotation drilling should only be utilised outside the contaminated site.

The size of the borehole is chosen in accordance with the intended screen dimension. With these types of borings, a relatively large screen dimension will be selected, such as 160 mm, 200 mm, or 250 mm. See Table 2.

The borings must have a concrete protective casing as the minimum protection. It may prove necessary to establish an actual dry well or, as an alternative, an insulated covering at ground level. Wells reaching lower groundwater aquifers must be reported to GEUS. Table 3 has an overview over recommended drilling methods.

Table 3
List of recommended drilling methods

 

Localisation soil borings

Investigation borings

Wells

Augering

x

x

x

Cable tool

 

x

x

Electrical log soil boring

x

x

 

Hollow-stem auger

x

x

 

Driven soil borings

x

 

 

Air drilling

 

 

x

Rotation drilling

 

 

x

 

During drilling, a record should be maintained stating:
Site, soil boring no., and date
Drilling method
Preliminary soil type assessment/classification
Recorded signs of contamination (discoloration, odour)
Stratum boundaries
Sampling depth
Drilling depth
Screen installation
Grouting
Water level observations

The screen installation should be described in a scale drawing. Water level observations made during soil boring should be indicated in relation to a permanent measuring point that can be found again later.

Normally, threaded PEH or PVC tubes are used as observation and screen pipes. The thread facilitates oil-free pipe connection.

Screen installation is carried out by means of slotted tubes packed with gravel. During screen installation, it can be expedient to place a length of casing to collect fine-grained material – a silt box.

The screen arrangement must be closed at the bottom using a PVC or wooden plug (not pressure-impregnated wood).

To account for possible blocking around the casing, soil borings that penetrate limestone rock or other hard rock must also have screens installed. The screen must be established near the aquifer layer. The screen installation should represent only one groundwater aquifer.

The screen can comprise the entire groundwater aquifer or parts thereof. By using short screens, low dilution and more depth-specific samples are obtained. However, this method also means that screens will normally be required at more levels, hence more samples for analysis will be necessary. In localisation borings where no real aquifer layer has been found, screens of 1-2 m are installed from the bottom of the boring.

By screens in connection with unconfined groundwater tables, the upper side of the screen should be above the water table to facilitate registration of any oil or similar substances floating on the water table as well as taking account of fluctuations. The screen must be packed with cleansed quartz silica sand. The gravel packing must be carefully monitored to ensure that all cavities between screen and wall of soil boring are filled in. This monitoring must ensure that the upper side of the gravel packing constitutes a solid foundation for the necessary grouting in the annular space between well casing and the wall of the boring above the screen.

When installing screens, screen materials must be selected to fit both the slots on the screen and the grain size. Emplacing the gravel pack could take place during water circulation. This ensures optimum packing of the screen gravel. The gravel pack should be led at least 0.5 m above the screen to avoid bentonite choking the screen. For the same reason it is advantageous to select finer-grade screen sand for the top 0.5 m. Immediately upon completion, the soil boring must be pumped clean to achieve optimum effect.

In certain circumstances it may be necessary to add water during soil boring as well as screen installation. The addition of water may be vital to the quality of soil boring as well as of screen installation and grouting. It is a requirement that the water used in connection with drilling and screen installation is uncontaminated tap water.

The purpose of grouting the well casing is to avoid unintentional spreading of contamination as a result of the soil boring. If contaminated soil strata with clay substrata are drilled through, it is important to carry out grouting with bentonite at the clay stratum. It must always be calculated on that natural barriers (e.g. stratification of the formation) will be destroyed during soil boring. These barriers are best restored by grouting along the entire length of hole without screens. Bentonite is used for grouting, whether bentonite powder or granulate. Grouting with "clay balls" alone will not suffice.

Granulate must always be poured into water. For this reason, water must be added to the space between casing and wall of soil boring if granulate is used above the groundwater table. An alternative is bentonite powder, which is stirred in a mixing vessel to a porridge-like consistency of bentonite slurry.

When grouting at ground level, the bentonite can be poured from ground level. When grouting at greater depth and beneath the groundwater level, liquid bentonite must be led down through a pipe (observation pipe) or pumped down using a special pump. In most cases the use of bentonite granulate is an alternative, possibly in the form of expanding bentonite. Granulate has the advantage of facilitating easier measurement of the location and thickness of the grouting during the grouting process. On the other hand, better contact between drilling hole and casing is obtained by using liquid bentonite /2/.

The location of the grouting depends on geological/hydrogeological conditions. The following figures show 4 main types of geological conditions with indications of correct location of groutings. In connection with shallow investigation soil borings (Figure 1) it is acceptable to fill the hole back up with extracted material (there should, however, always be a minimum seal of 1 m). The reason that this applies to shallow soil borings in particular is that soil boring has been carried out in the top soil strata and in groundwater aquifers near ground level. If these strata are already contaminated, the extracted material will not add any new contamination. If the top soil strata are uncontaminated, the backfill will likewise be uncontaminated.

Figure 1
Minimum seal of localisation boring with screens installed in aquifer near ground level.
  

Figure 2
Grouting of deep wells with screens installed in aquifer near ground level
   

Figure 3
Grouting of deep investigation well to a deep lower aquifer (overlying gravel strata in hydraulic contact with the limestone).
  

Figure 4
Grouting of deep investigation soil boring/well to deep lower aquifer (lower aquifer and aquifer near ground level are separate).

In connection with soil borings at contaminated sites it is necessary to consider the question of disposal of the extracted material. Regardless of the degree of contamination it is often unacceptable to leave the material at the investigated site.

Since disposing of contaminated soil can be costly, an aim during boring should be to separate uncontaminated soil from soil which is deemed to be contaminated. It would be advantageous to keep soil extracted from individual soil borings separate with an aim to subsequent separation of contaminated and uncontaminated soil. If there is any doubt whether or not soil is contaminated, it should be considered contaminated and treated accordingly.

Uncontaminated soil can be deposited at a landfill. However, contaminated soil must be turned in for treatment at a central processing plant. Consequently, final decisions as regards disposal must wait, pending the results of soil analyses.

All soil borings should be charted on a map and all soil borings with screens installed should also be levelled out. Borings are charted in relation to buildings or in a system of co-ordinates. In a minority of cases it may be necessary to level localisation borings in a relative datum system. In this case, a retrievable relative reference point is used. This relative fixed point is assigned the datum +180, preventing any doubt as to whether this is a relative or absolute datum. In connection with levelling the datum is set at ground level with a degree of accuracy of 0.1 metres and at observation point with a degree of accuracy of 0.01 metres (whenever possible, this should be to the highest point of the top of casing to avoid confusion). Marking the point of measurement facilitates recognition if the casing is subsequently shortened.

All borings must be safely abandoned when they are no longer needed. The guidelines in S. 15 of the Ministry of Environment and Energy Statutory Order No. 4, January 1980 must be followed when abandoning and grouting obsolete borings /3/. The owner of the boring is responsible for ensuring that abandoning procedure is carried out.

References

/1/ Hvam, T. Markundersøgelsesmetoder (‘Field Investigation Methods’). DGF-bulletin 5, September 1990.
[Tilbage]
  
/2/ Baumann, J. Kvalitetssoil boringer (‘Quality Soil borings’). Geologisk Nyt 4/1996.
[Tilbage]
  
/3/ Bekendtgørelse nr. 4 af 4. januar 1980 om udførelse af soil boringer efter grundvand (‘Statutory Order No 4, 4th of January 1980 on executing soil borings for groundwater’.) The Ministry of Environment and Energy.
[Tilbage]