| Front page | | Contents | | Previous
| | Next |
Shipbreaking in OECD
Inspection of Desguaces de la Arena ship dismantling facility, Northern Spain.
One of the identified ship dismantling facilities in Northern Spain was visited and
audited on 18 September 2002. Along the Spanish coastline, dismantling of ships has long
traditions. However, the activity has declined dramatically since mid 1980íes due to
stronger competition from outside Europe and in particular outside OECD territory. At
present, dismantling facilities still exists in Asturias (2), Santander (1-2), Bilbao
(1-2), Galicia (1-2) and Coruna (1). None of these facilities are organised in association
or similar industrial structures.
The company Desguaces de la Arena placed in Soto Del Barco in the Asturias Region of
Spain was founded in 1975 as a family company. The facility was erected on nature land by
establishment of new quarry areas with backfilling erecting a land surface of
approximately 18,000 m2. In the period since 1975, the facility has dismantled more than
300 ships equal to approximately 8-10 ships a year in average. However during recent years
most of the dismantling facilities in Spain have focussed on subsidised dismantling of
fisherman ships. Back in 2001, the latest major ships was dismantled at the facility (80-m
and 12-m width ship, totalling 2,110 tonnes). The primary dismantling has been
concentrated to former Russian military ships in various classes and sizes with a maximum
of 220-m in length. In peak period (1980-1990) more than 60 workers were employed at the
facility. At present only 4 workers are permanently employed.
As the facility is placed as an inlet facility (access through an inlet channel from
the Atlantic Sea - approximately 1.5 km), the depth of the inlet channel dimension the
size of ships available for dismantling. At present, the inlet channel has a maximum depth
of 6-m.
The facility is placed in an area of traditional dismantling activities. In 1970íes
not less that 4 different facilities were placed side by side. However, the only existing
facility - Desguaces de la Arena - has since the establishment been placed solely on the
eastern bank of the inlet channel.
Auditing Procedure
The site visit/auditing procedure was performed as a combination of forwarded
questionnaire (appendix A) and detailed interview by Managing Director Mr. Alberto Garcia
in combination with a site walk-over.
The Managing Director was quite open sharing information, and provided whatsoever
documentation on request (e.g. dates for authority site visit, air photos documenting
former activities and names of waste recipients for further contacting if found necessary.
The company has fulfilled the forwarded questionnaire the best way possible as a family
owned company with limited resources and in-depth knowledge on auditing procedures. The
company ensures for updated information e.g. new regulations, standards, accounting
principles etc. through their own managing board and through affiliated contracted
consulting services.
General Impression
The overall impression of the facility is an inconsistency in good housekeeping,
although recognising that this type of activities traditionally is in need of sufficient
space for further processing of the dismantled plates, cables, etc. The site area was
surrounded by fence, and immediate after entrance the auditor was approached by managing
workers. The ownership structure - family owned company - makes the facility vulnerable
for significant improvements due to limited human and financial resources. The close-down
of the three neighbouring ship dismantling facilities through the last decade is an
example hereof.
The capacity of the site range from 2-4 smaller fisherman ships as the lowest
affordable level of activity (present level) to 10-12 pcs of up to 220-m length ships.
However, due to lack of sufficient skilled working force, the maximum level will hardly be
accessible without substantial education of works man in e.g. welding. The present
capacity is also restricted due to decreasing possibilities for recycling of secondary
waste (machineries, radars etc). These components have due to increasing state
subsidiaries, hardly any value longer, why the attractiveness of dismantling ships are
almost solely related to world market price on steel.
The 95%-fractile dimensioned income from dismantling of ships - recyclable steel - is
sold through intermediate due to relatively minor annual production. In the past, the
facility sold directly to recycling factories in the region. The revenue costs for
recycled steel per tonnes was 90 EUR in August 2002 and 87 EUR in September 2002.
The facility operates under different procedures depending of the origin of the ships
allocated for dismantling:
 | Dismantling of fisherman ship, restricted market; |
 | Dismantling of other ships, free market. |
Subject: Fisherman ships. Dismantling of fisherman ships are restricted market
due to heavy state subsidies (EU support to lay-off of fisherman ships). The ships are
received, but hardly any prepayment is launch until the dismantling is completed. The
facility has 3-month from the incoming of the ship until the dismantling process must be
completed by authority inspection.
The facility must initially make a certification of the ship, that no off-gasses are
present before any dismantling activities. This certificate is performed by the facility
through an authorised person. During the period of dismantling, the facility should accept
to have both announced and non-announced inspections of the following authorities;
 | Government of Asturias; |
 | Government of Spain; |
 | Police; |
 | Environmental authorities; |
 | People Control (working environment). |
As an example of the regularity of these inspections, the auditor in below has
presented a list of inspections carried out by the most frequent authorities visiting the
facility - People Control (working environment, health and security) in the period of
1978-2002;
 | 14 September 1978; |
 | 30 October 1981; |
 | 8 July 1987; |
 | 27 December 1987; |
 | 21 April 1989; |
 | 11 December 1989; |
 | 6 February 1990; |
 | 19 October 1990; |
 | 19 December 1990; |
 | 13 November 1995; |
 | 10 April 2000. |
In the period from 1980-90, the authorities performed 8 visits, but in the decade
1990-2000 only 2 visits reflecting the dramatically fall in dismantling activities during
that period.
The managing director of the facility emphasised that the company has not track record
of any major problems with the authorities and has no track record of restricted orders
for improvement during the entire period of operation (almost 30 years). The auditor made
a control by looking through all official signed authorities record (copies to the
facilities from above implemented inspections), and can confirm that no immediate
restricted orders were outlined in the documentation.
Subject: Larger ships from the "commercial" market. Dismantling of larger
vessels from the commercial market operates in a more "free form". The facility
will and has only received vessels where all papers have been in accordance with
"normal procedures". The facility only has to fulfil the gas free certification.
Dismantling of such ships seems to be under slightly looser control by authorities due to
less mandatory requirements informing authorities about such activities (start document,
medium term inspections (often not carried out) and completion document (no inspections).
In principle such activities can undergo with only one inspection beside whatsoever
non-announced inspection which according to above listed dates can be in-between years.
The facility claimed to be in possession of a dry-dock, which was inspected. The
"dry-dock" was an emptied side-channel which at low tide could allow cutting or
larger fraction on dry land. There was no supportive facilities at the
"dry-dock" area, which although could be connected to the fact, that this area
in latest year main was used a reserve area for ships waiting for dismantling. The
"dry-dock" area is not in a condition justifying allowances for dry-dock
dismantling activities. Certain improvements are needed prior to such certification.
Waste handling
Dismantling of ship is a necessity due to constant ageing of ships, change of standards
for bulk carrying etc. The dismantling activity will inevitably generate different kind of
waste and waste streams. Depending of the magnitude of generated and/or produced waste
dismantling facilities perform their own services or operate through intermediating
companies. The visited facility works only through intermediating companies.
Initially, all content of oil is pumped to a 2 tank on-land system, which in emptied on
regularly basis by an authorised company Vigon (subsidiary of the authorised and
obligatory company Cogersa, which operates in the Asturias province under the supervision
of the authorities). The oil also works as an income source for the company.
Any produced clean metal is sold through intermediating company for recycling (income
source). The metal was placed on pure uncovered ground (originally infill material).
Wood (all kinds - clean, painted, impregnated) are sold directly to privates by the
company (income source). The wood was kept in stables for further processing.
Steel - sold through intermediating company (largest income source). The steel was
placed on pure ground.
Machinery and or auxiliaries are sold in case of profit; otherwise the items are more
or less without any control (partly stored on the area alternatively presumably disposed
off somewhere). The machineries and other auxiliaries were placed directly on the
unprotected ground.
Cables are sold through intermediating company. The price on cables depends on the
cleanness of the cables. No immediate information accessible on incentives to keep
"dirty" cables instead of "clean" cables. The cables were stored in
top opened iron containers.
Additional waste (insulation, various metals, wires etc) must be disposed of through an
authorised company Cogersa, licensed to operate in the Asturias Province of Spain, which
according to the managing director makes up a monopole situation leading to increasing
prices and no competition. The additional waste were mixed together and stored directly on
pure ground.
Mandatory reporting requirements
The facility must make the following annual reporting to relevant authorities.
 | Annual MARPOL document for the Spanish authorities outlining which activities have been
undertaken and waste disposed of; |
 | Annual report to Government of Spain outlining the amount of oil disposed of through
Vigon (company of Cogersa) and amount of steel sold for recycling. |
 | In connection with dismantling activities the certification for hot work, completion
certificate and normal track recording of waste streams is mandatory although it seems as
the facility as such is not operated under a license outlining e.g. environmental demands
for operation. |
Occupational Health and Safety
The facility was during the auditing operating in lowest possible mode (4 workers and 2
managerial persons). The officers performing cutting was wearing gloves, boats, special
clothing and partly helmet and air-breathing protective gear. They also wear eye
protective gear while cutting. However, the equipment seemed old and not fully updated.
The cutting was only performed in the free and partly on plan surfaces while others were
working on unstable ground cutting up the dismantled steel plates.
At the facility in total 4 workers was performing dismantling of fisherman ships. The
workers are divided into 3 categorises;
 | 1st officer - Performs cutting and training of 2nd and 3rd
officers; |
 | 2nd officer - also performs cutting, but are not in charge; |
 | 3rd officer - makes no cutting. |
The pressure bottles were secure and areas for refilling fenced not allowing the larger
central pressure tank to have physical contact with torch gas.
The overall impression is that most required safety and protective gear was in place,
although not fully used in accordance with regulations. The facility was so small that no
safety organisation was in place. The different waste fractions were separated, although
only cables and certain types of metals were kept in bottom-closed containers. All other
waste fractions were disposed directly on the ground. The facility operates presumably in
accordance with Spanish regulations but the overall impression is that the facility is
under close-down due to constant stronger competition from non-OECD facilities on the
commercial and much more profitable market for ship dismantling. The owner (son of the
original founder of the company) has no plans for future expansion or taken over by
others. The company will most likely operate on dismantling of fisherman ships under the
EU-regulations on fishing fleet, and ultimately close down the activities hereinafter.
The company is an excellent show case outlining the consequences and impacts on in-side
OECD dismantling capacity from a competitive market mainly driven by non-OECD placed
facilities with far less official control. The two-sided market with a subsidised
programme for fisherman ships with the EU-region and a commercial market must be tighten
up together in an OECD context allowing the remaining few facilities within OECD with a
potential as host facilities for larger ships/vessels to operate on proper commercial
conditions encouraging the companies to perform necessary investment into new equipment,
still improving working conditions and waste handling procedures.
Options for Improvement
If the Desguaces de la Arena plot should serve as commercial and advisable facility for
e.g. dismantling of Danish ships, the below mentioned recommendations for improvements
should be enforced and implemented;
 | Establishment of authorities procedures in a clear context and format, including clear
agreements with not only National authorities, but also provincial authorities in e.g.
Asturias; |
 | Improved documentation of waste streams; |
 | Establishment of a formal safety organisation on the plot; |
 | Improve house keeping strongly related to imposed guidelines for waste stream handling
routines and dispose-off; |
 | Clear and consist cooperation between involved authorities and e.g. the Basel
Secretariat due to possibilities for export of hazardous substances. |
Assessment of Basel Draft Guideline (TWG 19, Revision 2) Compliance
Assessment of the compliance with Basel TWG 19, revision 2 technical guideline is
performed in accordance with Table 11 on "Generic checklist for closing the gaps -
achieving ESM-compliance".
Focus area |
Existing practise and
standards |
Assessment of
compliance with 1, 5 and/or 10 year recommendations for implementation actions. |
Physical identification
and labelling on boards |
identification
implemented, but labelling missing |
Upgrading on labelling
required for 1-year compliance.
Substantial improvements in establishment of transfer
operation facilities needed for 5-year compliance.
Full lining required in HW management areas for
10-years compliance. |
Cleaning of oil
tanks/compartments before hot work commences |
compliance due to oil
collecting tanks and gas certification before hot work commencement |
Establishment of spill
boom needed for 5-years compliance.
Improvement of draining and pumping facilities required
for 10-years compliance. |
Use solvent for dissolve
heavyweight sludge (accessible for pumping) |
Not immediate sludge
treatment due to minor problem area |
Facilities for containment
of solvent and dissolved sludge required for both 1 and 5/10 years compliance. |
Ventilate
compartments/tanks continuously |
Not active ventilation
installed, only passive |
Facilities for activated
ventilation required for both 1 and 5/10 compliance. Furthermore establishment of storm
water and oil spill boom required for 5 and 10-years compliance. |
Introduce hot work
certification |
Has own system with 1st,
2nd and 3rd Officers |
Official certification
(closely related to OH&S in general) required for 5 and 10-years compliance. |
Test of compartments for
presence of e.g. off-gasses |
Existing gas certification
at commencement |
More regular monitoring of
gasses, compartmenting of e.g. asbestos material, and dedicate and facilitated areas for
HW handling required for 5 and 10-years compliance. |
Provide adequate storage
facilities for hazardous wastes |
Only oily and cables
contained in separate containers |
More consistent approach
and container facilities needed for obtainment of both 5 and 10-years compliance. |
Test of presence of e.g.
toxics, corrosives, irritants prior to manual activities |
No implemented procedure
present at the site area |
Establishment of testing
procedures for identification of selected waste types for 1-year compliance. Separated
procedures and supportive facilities for waste segregation (e.g. asbestos) need for 5
years compliance. |
Identification and removal
of flammable painting prior to cutting activities |
No immediate procedures
implemented |
Procedures for
identification and operational practise (including containment of residues from
procedures) needed for 5-years compliance. |
Spill clean up and
notification |
No oil spill equipment
present and no notification procedures implemented beside annual MARPOL and central
authorities reporting on recycled steel and disposed off oil products |
Procurement and
operational practise established is needed on oil spill. Review and improvement of
notification procedures needed for 5-years compliance. |
General occupational
health |
Personal protective gear
present at the facility |
Strengthening and
improvement of procedures/purchasing of equipment for personal protective gear (rigid
helmets, gloves, possibility for respiratory equipment, fire extinguishers, food wear etc)
is needed for 1-years compliance. |
Additional |
Good housekeeping and
improved workers safety and recipient monitoring |
The facility need to
further strengthen selected procedures related to special waste types and in particular
asbestos waste, general improvement of workers safety and protective gear beside general
concern related to unintended pollution of non-lined surface and nearby water inlet water
bodies. |
Additional visit to Dismantling facility in Gijon
The auditor performed an additional visit to a similar ship dismantling facility
situation in the harbour area of Gijon - Muelle de la Osa on 19 September 2002. It was not
possible for the auditor to meet with the managing director of the facility during the
stay in the region, although the auditor did some observation of relevance for this study.
 | The facility was fenced by concrete wall and the estimated size was 150 times 150-m,
equal to approximately 20,000 m2; |
 | The facility was in activity dismantling a medium fisher man ship and a minor fisherman
ship was waiting in line for dismantling; |
 | The facility was only able of performing dismantling along a quarry, not option for
dry-dock or similar; |
 | During the visit approximately 10 persons were observed on the plot, of which 5-6 were
cutting; |
 | The site area was kept in the same way as the Desguaces de la Arena site area, although
there was no observation of any containers for safe keeping of waste fractions.
Furthermore, a small fire was identified presumable disposing of wood and additional waste
without clear identification. |
 | The overall impression was that the site was operated more or less similar to the
Desguaces de la Arena site, although slightly more activity was observed. |
| Front page | | Contents | | Previous
| | Next | | Top | |