Potential for Application of Reclaimed Water for Industrial Purposes, and Identification of Risks

Summary and conclusions

Introduction and Objectives

Reclaimed water defined as storm water, greywater, water from industrial processes and water discharges from remediation pumping can be used as a water resource in the industry. For some industrial purposes the recovered water does not need to comply with the drinking-water quality requirements usually applied.

The present project completed within "Aktionsplan for fremme af økologisk byfornyelse og spildevandsrensning" (Action Plan for Urban Development and Wastewater Treatment) comprises an evaluation of potential sources for production and reuse of "reclaimed water" in industry.

According to the "Project document" describing the scope of work, the objectives of the project are the following:

  • To identify industries in Denmark with potential water sources suitable for production of reclaimed water
  • To identify special areas where reclaimed water can substitute water with drinking-water quality
  • To identify potential risks related to reuse of reclaimed water
  • To evaluate the contractual relationship between a "Producer" and "Receiver" of reclaimed water
  • To prepare a draft "Standard Contract" for such a relationship.

Screening of Reclaimed Water Sources and Areas of Reuse/Recovery

Water consumption, wastewater discharge and specific areas of water use within industry were evaluated based on old data originating from a survey from 1993-94, which is reported in /1/.

It was concluded that the total water consumption by industry was 165 million m³ per year and the discharge of wastewater was 147 million m³ per year. The difference due to the method of data compilation.

The survey concluded that the major areas of industrial water consumption were the following:

  • Cooling 57%
  • Washing/flushing and cleaning 16%

Water directly introduced to the "product" only comprised 2% of the total consumption. The use of reclaimed water was not included in the survey and can consequently not be evaluated.

An additional survey has been conducted under the present project comprising an evaluation of approximately 320 large-scale industries' "Green Accounts" for year 2000-01.

Table A below summarises the use water by industry based on information from the "Green Accounts". The source of data is the database operated by the Danish Commerce and Companies Agency named "WWW.Publi-com.dk"/13/.

The table indicates that "Sea water" is the largest water source in the categories of "Power and Heating plants" and "Vegetable and Meat Processing Industry" (generally named Food Processing Industry).

Furthermore, it is concluded that approximately 37% of the water consumption originates from public or private water supply, meaning that the water has drinking-water quality.

Table A: Overview – Industrial Water Consumption in 2000-01, 320 large-scale industries

Click here to see Table A

From the table it can also be concluded that use of "Reclaimed water" only contributes with 0.2% of the total industrial water consumption.

However, it is evaluated that the data source (Green Accounts) is incomplete, due to the fact that some industries only provide information regarding total water consumption and do not give information about the water source.

It is anticipated that more accurate information from a new survey would not change the conclusion that the reuse of reclaimed water by industry is limited.

The potential of discharges from remediation pumping comprising polluted water from groundwater pumping is based on a survey conducted by "Amternes Videncenter for Jordforurening" (The County Authority's Knowledge Centre for Soil Pollution) in 1996-97.

Based on the results from this survey it is concluded that the total "Discharge from Remediation Pumping" was approximately 5.4 million m³ in 1997. Approximately 70% originated from the County of Copenhagen and only 8% was reused as second quality water. The remaining part was either discharged into public sewers or to the environment (river, lakes or sea).

It is evaluated that reuse of reclaimed storm water, process water and ground water cannot be used in production or added to manufactured goods during processing.

Reuse of reclaimed water must be limited to purposes where the water is not directly in contact with the product, otherwise the risk of product contamination or the impact on the manufactured goods is simply too high.

Introducing the reclaimed water in the production process, for example as washing or flushing water, may have a serious impact on the quality of the manufactured goods.

The economic benefit of using reclaimed water instead of water from deep wells is often limited and the risk can be high. Consequently, comprehensive risk assessment should be conducted before it is decided to use reclaimed water in the production process.

Reuse of reclaimed water might cause problems with approval from relevant authorities namely The Factories Inspectorate and The Danish Veterinary and Food Administration (Food Inspection).

Accordingly, the present project proposes reuse of reclaimed water outside the production process.

Detailed Study of Pilot Installations

Pilot studies have been conducted on the following three Danish installations:

  • Danisco Sugar in Nakskov (Sugar Beet Factory)
  • Novozymes A/S in Kalundborg (Biotechnical Factory)
  • CP Kelco (old Copenhagen Pectin) in Ll. Skensved (Pectin Factory)

T table below summarises the water consumption, the water discharge and the reuse of reclaimed water in 2001-02.

Table B: Key Water Data from Danisco sugar's, Novozymes A/S's and CP Kelco's Green Accounts, 2001-02

Water consumption/discharges Danisco SugarNakskov
(in m³/year)
Novozymes A/SKalundborg
(in m³/year)
CP KelcoLl. Skensved
(in m³/year)
Water Consumption 534,000 1,576,000 1,718,000
Wastewater Discharge 1,250,000 1,399,000 1,298,000
Reclaimed Water None approx. 200,000 132,000

Reclaimed Water Sources and Areas of Reuse

Firstly the present water consumption, water usage and discharges was examined at process unit level at each factory.

Secondly the present sources and new potential sources of reclaimed wastewater were identified.

The results comprising reclaimed water sources and potential areas for reuse are summarised in the table below.

Table C: Reclaimed Water Sources and Reuse Areas at Danisco Sugar, CP Kelco, and Novozymes A/S

Industry Reclaimed Water Source Intern al
or Extern al
Area of Reuse
(Process)
Yearly Flow m³/år
Danisco Sugar, Nakskov Surplus condensate Internal Gas Washer 30,000
  Surplus condensate Internal Juice extraction 4,000
  Surplus condensate Internal Flush water box (1) 224,000
  Surplus condensate Internal Flushing -
  Surplus condensate Internal Fly ash plant 20,000
  Surplus condensate Internal Cooling of feed pumps 13,000
  Surplus condensate Internal Sulphur cooling 131,000
  Surplus condensate Internal CO2-pumps 33,000
  Grader water (2) Internal OF condenser 217,000
  Surplus condensate Internal OF cooling  
Novozymes A/S, Kalundborg Pre-treated wastewater Internal Secondary polymer mixing 162,000
  Pre-treated wastewater Internal Mixing of scum oil 5,000
  Pre-treated wastewater Internal Lime mixing 56,000
CP Kelco, Ll. Skensved Discharge from remediation pumping(TCE-water) External Make-up water for cooling towers 130,000
  Condensate Internal Flushing of cloth, Juice pressing 10-20,000

Note:
(1) Project "Reuse of condensate in flush water box" was completed in 2003.
(2) Grader water= water from cooling tower

Identified Risks of Reusing Reclaimed Water

An overall risk assessment related to the reuse of reclaimed water should comprise the following main areas:

  • Hygienic risks
  • Occupational health and safety risks
  • Environmental impacts (wastewater discharges, air emissions and waste disposal)
  • Technical risks.

An overall risk assessment has been conducted at each participating installation. The results are summarised in the table overleaf.

Table D: Summarised Risk Assessment at Danisco Sugar, Novozymes A/S and CP Kelco

Danisco Sugar, Nakskov
Risk Area Identified Risk Hazardous Area, Chemical Substances or Other Risk
Hygienic Risks • Limited as sanitary wastewater is discharged in separate system
• Failure in connections and operation may occur
• Pathogenic bacteria
Occupational Health and Safety Risks • Odour emission • Ammonia
  • Scalding hot water (Condensate) • Temperature on condensate (>60 °C)
Environmental Impacts • Odour • Ammonia and H2S
Technical Risks • Reliability of supply • Function of distribution system, e.g. heat exchangers at anaerobic plant
  • Process breakdown, anaerobic plant • Emergency supplies of inlet water
  • Precipitation clogging of pipes, valves and pumps • CaO
  • Start-up and running-in of anaerobic plant • Supply of cooled condensate
• Spare supply from inlet water remain
Novozymes A/S, Kalundborg
Risk Area Identified Risk Hazardous Area, Chemical Substances or Other Risk
Hygienic Risks • Limited as sanitary wastewater is discharged in separate system
• Failure in connections and operation may occur
• -Pathogenic bacteria
Occupational Health and Safety Risks • None -
Environmental Impacts • Wastewater and sludge • GMO
Technical Risks • Inactivation of polymer • Salts, increased polymer usage
CP Kelco, Ll. Skensved
Risk Area Identified Risk Hazardous Area, Chemical Substances or Other Risk
Hygienic Risks • Limited as sanitary wastewater is discharged in separate system
• Failure in connections and operation may occur
• -Pathogenic bacteria
Occupational Health and Safety Risks • None -
Environmental Impacts • Emission from cooling tower • Trichloroethylene
Technical Risks • Pump failure on external system
• Power failure on internal water treatment system
• Supply reliability.
• Permit for deep well ground water supply is kept as reserve

Economic Evaluation of Reclaimed Systems

Key economic data comprising investment costs, net savings and payback period are summarised in the table overleaf.

Table E: Summarised Investment Costs, Net Savings and Payback Period for Reclaimed Water System Projects

Danisco Sugar, Nakskov
Project Investment CostsDKK Net SavingsDKK per year Payback PeriodYears
Project 1: Reuse of condensate in Flush water box 75,0000 -16,000 -
Project 2: Establishment of air-cooling for turbine oil 1,104,000 - -
Project 3: Reuse condensate for cooling of CO2 pumps 288,000 -73,000 -
Project 4: Cooling of surface Condenser with fall water 604,000 -130,000 -
Novozymes A/S, Kalundborg
Project Investment CostsDKK Net SavingsDKK per year Payback PeriodYears
Secondary polymer mixing - 1,000 -
Mixing of scum oil - 32,ooo -
Lime mixing - 11,000 -
CP Kelco, Ll. Skensved
Project Investment CostsDKK Net SavingsDKK per year Payback PeriodYears
Reuse of discharge from remediation pumping 1,470,000 (1) 861,000 1.2

Note: (1) Exclusive of compensation DKK 400,000.

Contract Agreements between Producer and Receiver of Reclaimed Water

The contract conditions relating to delivery and receipt of reclaimed water can be revealed through consideration of the following issues:

  • Operational Economic Incentives
  • Regulations and Statutory Orders
  • Producers Services
  • Receivers Services
  • Force Majeure
  • Failure in the Supply
  • Failure in Service Provided
  • Failure to Pay
  • Failure to Receive
  • Disputes

If reclaimed water is exchanged between two parties (eg. a private company and public authority or between two private companies) it is recommended to sign a written Contract Agreement between the two parties.

The Contract Agreement can be based on the draft standard form in Annex D, named "Forslag til standardaftale – Levering af sekundavand". (Draft Standard Agreement between Producer and Receiver of Reclaimed Water).

Conclusions and Recommendations

The present project has identified possible supply sources of reclaimed water within the following industry categories:

  • Power and heating plants
  • Chemical and biological production
  • Vegetable production

Use of reclaimed water is proposed in the following areas of the industrial production process:

  • Process cooling
  • Make-up water for cooling towers
  • Cleaning (outside the production process)
  • Internal pre-treatment of wastewater (mixing of chemicals)
  • Air purification, flue gas purification and odour treatment plants

An overall risk assessment related to the reuse of reclaimed water should comprise the following main areas:

  • Hygienic risks
  • Occupational health and safety risks
  • Environmental impacts
  • Technical risks

Reuse of reclaimed water can have consequences for occupational health and safety as well as the environment, e.g. wastewater discharges, air emissions and solid waste disposal. These consequences must be carefully evaluated under each project.

Technical issues should include assessments of how reserve water supplies (deep well or public/private water supply) should be maintained as emergency supplies. Necessary permits or exemption possibilities to use other supplies should be organised to cover the event of failure in normal supplies or if the quality of the reclaimed water does not comply with required quality.

Reliable emergency supply must be available at short notice securing production failure and any loss of income as a result of supply failure.

Previous research studies /2/ have indicated that a yearly volume of minimum 50,000 m³/year must be available before a project becomes economically feasible.

The economic evaluation conducted under the present project indicates that the reclaimed water must replace drinking water, which is bought outside the company and that a water tariff of more than DKK 5-10 /m³ must be paid before a project is feasible.

The economic evaluation of reclaimed water systems has verified that projects where reclaimed water substitutes non-drinking water from sources like the sea, lakes or rivers are not feasible because of low production costs (< DKK 1 /m³).

Catalogue of Possible Project Areas for Reclaimed Water Systems

Finally a catalogue of areas and industry categories with potential of introducing reclaimed water systems has been prepared.

The list is summarised in the table overleaf.

Table F: Catalogue of Possible Project Areas for Reclaimed Water Systems

Factory Category Source of Reclaimed Water Area of Reuse
List no. Main Group Water Type Usage
B Cement, lime and chalk production • Storm water • Product (suspension)
D Chemical and biological production • Cooling water • Cooling
• Cleaning
E Vegetable production • Process water (purified wastewater)
• Storm water
• Cooling
• Media transport
G Power and heating plants • Cooling water
• Process water, discharge from remediation pumping
• Flue gas purification
J Protein- and pectin production • Reuse of Cooling water
• Reuse of discharge from remediation pumping
• Cooling water
• Cleaning
- Reuse of discharge from remediation pumping • Remediation pumping from soil pollution.
• Deep well ground water extraction from construction sites
• Cooling water

A list of 17 industries with either potential for production or reuse of reclaimed water has been prepared. The list, which comprises relevant pilot-project installations, appears in chapter 3.6.2 of the present report.

However it should be noted that the funds under "Aktionsplanen for fremme af økologisk byfornyelse og spildevandsrensning" (Action Plan for Urban Development and Wastewater Treatment) for conducting such studies are not available in the 2004 budget allocation.

 



Version 1.0 April 2004, © Miljøstyrelsen.